← Empire State Building wall half: all sets
Empire State Building wall half: 4 ft (1:363.5) · 121.9 cm
Putting it together and hanging it. 4 ft (1:363.5), 121.9 cm (48.0 in) tall, 36.6 cm (14.4 in) wide. 5 printed pieces, 6 keys and a wall cleat.
Before you start
At 4 ft (1:363.5) it is 121.9 cm (48.0 in) tall and 36.6 cm (14.4 in) wide, and hangs 4.3 cm (1.7 in) out from the wall. It comes in 5 printed pieces that join with printed keys: no glue.
- Work on a big table or the floor, on a folded towel.
- It hangs from one small cleat with 2 screws. You need a drill, a spirit level, a pencil and a tape measure, and 2 countersunk screws (4 mm / No. 8, 30 mm long) with wall plugs to suit your wall.
- Optional: 6 small cable ties (up to 4 mm wide) for an extra hold.
The piece you are moving is orange. There is a printable PDF of these steps at the top of this panel.
What's in the box
- Base
- Lower tower
- Middle tower
- Upper tower
- Mast
- 6 bow-tie keys, 2 mast dowels and the wall cleat.
The building is hollow and open at the back, so light can shine through the windows.
Lay it face down
Lay the base face down on a folded towel, back facing up. Everything that joins the building together goes in from the back.
Join the lower tower to the base
Slide the lower tower on to the base. A thin lip inside the base's walls slips inside the lower tower and lines the two up. It also stops light leaking through the seam.
Push them together until the seam is closed all the way round.
Press in the keys
A bow-tie pocket crosses the seam on the back of each side block. Press a key into each pocket, narrow chamfered face first, until it sits flush with the back. Firm thumb pressure, never a hammer.
To take a key out, lever it from the small notch under its lower point.
Cable ties (optional)
The keys hold the joint on their own. For an extra hold, use the small loop on the inside face of each block, which spans the seam: feed a cable tie up through the loop, round its bar and back, pull it tight and snip the tail.
Ties also hold a light string in place.
Add the middle tower
Join the middle tower to the lower tower the same way: slide it on, press in two keys, then add the ties if you are using them.
Add the upper tower
Join the upper tower to the middle tower the same way: slide it on, press in two keys, then add the ties if you are using them.
The upper tower has the hanging lip moulded across its back, just above its bottom edge. If you use ties here, each one runs down through the slot in the end of the lip before it goes round the loop.
Lights (optional)
Lay a string of battery fairy lights inside the hollow back. About 2 m of small warm-white bulbs fills it nicely. Run the battery box or lead out through the notch in the bottom edge of the base. Hold the string in place with the cable ties.
LED only: no bulbs that get hot.
Then check every seam is closed and every key flush. Leave the mast off for now.
Fix the cleat to the wall
Mark where you want the bottom of the building. Measure up 75.5 cm (29.7 in) and draw a level line about 10 cm long. That line is the top of the cleat. Mark the middle of the line.
Hold the cleat with its top edge on the line, centred on your mark. The slope runs down towards the wall and the countersunk holes face you. Check it is level, mark the two holes (24 mm apart), drill and plug them to suit your wall (plasterboard fixings on stud walls) and screw it on. The screw heads must sit flush or just below the surface.
You need a clear patch of wall 36.6 cm (14.4 in) wide and 121.9 cm (48.0 in) tall, out of strong sun and away from radiators. The plastic softens above about 55 °C.
Lift it on
Lift the building upright with one hand under the base and one behind the middle. Hold it flat to the wall with the lip a little above the cleat, then lower it until the lip drops down behind the cleat. The slope pulls it in to the wall.
Slide it sideways to centre it: it moves up to 28 mm (1.1 in) each way. Press the base gently towards the wall. It should sit flat.
How it holds
Seen from behind, with the wall taken away. The lip on the back of the upper tower sits down behind the cleat's slope, so the building's own weight pulls it in to the wall. It can't lift off by accident.
Fit the mast
Push the two dowels into the holes in the top of the upper tower, about halfway. Then press the mast straight down on to them until it sits tight. Steady the top of the building with your other hand while you press.
Done
That's it. To take it down, lift the mast off first, then lift the building straight up about 1 cm (1/2 in) to free the lip and bring it away from the wall.
Dust it with a soft dry brush or a hair dryer on cold. No water or sprays. If a seam opens, press the key back in.
Something not right? Send me a message on Etsy with a photo and I'll sort it out.